The hidden cash trap: when your deposit schedule leaves you floating the job
Modular companies run on deposits. The customer pays as the job moves along, and that money is supposed to cover the work. Most of the time it does.
The trouble starts when the deposits and the spending don’t line up. If you buy materials or start sitework before the matching deposit comes in, you’re paying for the customer’s project with your own cash. That’s what I mean by floating the job: your money covers the gap until the customer’s deposit catches up. A few weeks of that is normal. Leave it too long, or have a customer pay a deposit late, and that’s how a profitable modular company ends up in a cash crunch nobody saw coming.
How a modular deposit schedule works
Every modular contract has a deposit schedule. Here’s a common one on a $1M job:
- 10% when the contract is signed
- 30% when production starts
- 30% when the modules leave the factory
- 20% at install/set
- 10% at completion
On paper, that looks safe. The customer has paid 40% before the first module is built.
Where the money actually goes
Your spending runs on a different calendar. Two costs jump the line.
Factory materials. Lumber, steel, windows, and everything else has to be on the floor before production starts. So you order it, and usually pay for it, weeks before the production deposit lands.
Sitework. Foundations, utilities, and grading happen while the modules are still in the factory. The crews get paid as they go. The customer usually doesn’t pay for any of it until the modules ship or get installed.
Here’s the same $1M job, with what the customer pays and what you spend at each stage:
One $1M job (example numbers)
| Stage | Customer pays | You spend | Running gap |
|---|---|---|---|
| Contract signed | $100K | $0 | $100K ahead |
| Design freeze, materials ordered | $0 | $370K | $270K behind |
| Production starts | $300K | $60K | $30K behind |
| Modules in production, sitework starts | $0 | $140K | $170K behind |
| Modules ship | $300K | $120K | $10K ahead |
| Install/set | $200K | $70K | $140K ahead |
| Completion | $100K | $30K | $210K ahead |
Swipe sideways to see every column.
The job makes $210K. But twice along the way, you’re carrying it with your own money.
When deposits fall behind, you’re floating the job
Put the two on one chart and the gaps are easy to see.
- Deposits received
- Cash spent
- You’re floating the job
Example $1M job. The shaded months are when you’ve spent more on the job than the customer has paid you.
See the numbers
| Months from signing | Deposits received | Cash spent |
|---|---|---|
| Signing | $100K | $0 |
| Month 1 | $100K | $20K |
| Month 2 | $100K | $370K |
| Month 3 | $400K | $430K |
| Month 4 | $400K | $570K |
| Month 5 | $700K | $690K |
| Month 6 | $900K | $760K |
| Month 7 | $900K | $790K |
| Month 8 | $1M | $790K |
| Month 9 | $1M | $790K |
Every shaded month is your cash paying for the customer’s project. On this job it peaks at $270K, the month the materials get paid.
That’s fine if you know it’s coming and you have the cash. The problem is that most owners don’t track it job by job. They see the bank balance, and the bank balance is still full of deposits from other jobs. So it looks fine right up until it isn’t.
What happens when a deposit is late
Now say the customer pays the production deposit two months late. Maybe their financing is slow, or they’re arguing about a change order. The factory doesn’t stop, the sitework crew doesn’t stop, and the bills don’t stop.
- Deposit paid on time
- Deposit paid 2 months late
Same example $1M job. The dashed line is the cash you have to cover it: your bank balance minus the deposits you’re holding for other jobs. One late deposit almost doubles what you’re carrying.
See the numbers
| Months from signing | Deposit paid on time | Deposit paid 2 months late |
|---|---|---|
| Signing | $0 | $0 |
| Month 1 | $0 | $0 |
| Month 2 | $270K | $270K |
| Month 3 | $30K | $330K |
| Month 4 | $170K | $470K |
| Month 5 | $0 | $0 |
| Month 6 | $0 | $0 |
| Month 7 | $0 | $0 |
| Month 8 | $0 | $0 |
| Month 9 | $0 | $0 |
One late deposit and you’re carrying $470K instead of $270K, and the gap never closes in between. Say you have $300K of your own cash to cover it. That’s your bank balance minus the deposits you’re holding for other jobs. On time, the job never needs more than $270K, so you’re fine. Late, it needs $470K, and you’re $170K short. Now multiply that across every job in the plant at the same time.
That’s the cash crunch. Not because the job loses money. It doesn’t. It’s because the money shows up after you’ve already spent it.
How to keep deposits ahead of the spending
You don’t need new software to fix this. You need to look at timing, job by job.
- Map every job. For each one, list when each deposit is due and when you’ll actually pay for materials and sitework. The weeks where spending comes first are the weeks you’re floating it.
- Tie deposits to the spending. If materials get paid at design freeze, make a deposit due at design freeze, not at production start. If sitework starts before the modules ship, bill for it when it starts.
- Don’t order until the deposit clears. Make it a rule: no material PO goes out until the matching deposit is in the bank.
- Chase late deposits every week. A deposit that’s two weeks late is a cash problem, not a sales problem. Someone should be calling about it.
- Know your reserve number. Add up the gap across every open job, month by month. The biggest month is how much cash you need on hand. If your bank balance minus the deposits you’re holding is less than that, something has to change: the deposit schedule, the order dates, or a line of credit.
If you don’t know which of your jobs you’re floating right now, that’s the first thing to find out. Our Billing and AR support gets deposit invoices out on time and puts every late one on a list your team sees every Friday. And if you want help tracking your cash, book a 15-minute call.
Four Accounting: accounting for modular construction companies